Producing gas offshore is not enough to secure electricity: it must also be transported to power plants. In Senegal, the next gas pipelines are intended to connect offshore resources to production sites and industrial facilities. Their financing and schedule will determine whether this ambition translates into a tangible contribution to the country’s energy supply.
Connecting fields to places of consumption
The Senegal Gas Network (RGS), a majority state-owned company responsible for transporting gas by pipeline, is planning a new phase of development. Its chief executive, Pape Momar Lo, presented a programme of three sections requiring €530 million, or about $594 million, at African Energy Week in Cape Town. Reuters and the event organiser reported the announcement, made in October 2026.
Construction could begin in 2027, with operations targeted to start in 2029. The project comprises sections named Green, Blue and Orange. According to specifications presented by the RGS, together they would amount to 255 kilometres of pipelines. Technical studies are said to be complete, but the funding still needs to be secured.
The Green section is estimated to cost €220 million for 110 kilometres. Its stated capacity is 300 million standard cubic feet per day. It is intended to carry gas from the Greater Tortue Ahmeyim (GTA) offshore project, shared with Mauritania, to other parts of the network.
The Blue section would represent €180 million and 100 kilometres of pipelines. Its stated capacity is 713 million standard cubic feet per day. It would serve six power plants and six industrial facilities. The Orange section, priced at €130 million for 45 kilometres, would serve six industrial sites and one power plant. These figures describe the programme presented by the RGS; they remain contingent on the announced configuration and infrastructure projects.
The estimates include €25 million in compensation for people affected by the works. This item is a reminder that pipeline routes involve more than engineering and financing: they also affect residents and economic activities along the way.
A first pipeline is already under construction
This extension would build on a first section, whose construction began in September 2026. Valued at €275 million, it is intended to connect the GTA gas hub to the Gandon power plant, which is planned to have a capacity of 250 megawatts. The RGS said the northern part of the works was 25.8% complete when it presented the new programme. The company confirms that construction has started at Gandon and describes a pipeline of about 85 kilometres.
Ultimately, the network is intended to connect several production and consumption hubs, notably around GTA, Yakaar-Teranga and Sangomar. The project supports the so-called “gas-to-power” strategy — using gas to generate electricity — and “gas-to-industry”, which involves supplying it to businesses. The RGS is majority-owned by PETROSEN, with FONSIS and Senelec among its shareholders.
To attract partners, the proposed framework provides for a renewable 15-year concession and a tariff structure intended to cover investment and operating costs. The RGS chief executive has also put forward an internal rate of return of 20%. This stated return is a proposal for investors, not a guarantee of results for the public. Final terms will depend on contracts, the risks borne by each partner and the network’s actual revenues.
Gas alone will not resolve electricity-sector weaknesses
In September, electricity supply was disrupted. Senelec cited maintenance and network-strengthening operations, as well as technical constraints that temporarily affected production. RTS reported these explanations and the company’s announcement that conditions would gradually return to normal. The episode is a reminder that continuity of service depends on fuels, power plant availability and the condition of equipment.
Transporting gas could diversify the supply of some power plants and reduce their reliance on imported fuels. But the effect on electricity costs is not automatic. It will depend on gas availability, transport charges, the price paid by power plants and their ability to operate. Households and small businesses, particularly in areas where service is unreliable, will benefit from improvements only if these gains feed through to generation and distribution.
The same caution applies to industrialisation. A more predictable supply could support industrial sites along the corridors served. However, the route, compensation, tariffs and terms of access to the network will affect the benefits for businesses and neighbouring communities. The announced commitments will therefore need to translate into transparent rules and verifiable results.
A national issue with regional implications
Senegal is developing this infrastructure in a region where energy security and exchanges between countries remain important issues. The GTA project is cross-border with Mauritania, while the planned gas pipelines are primarily intended to connect Senegalese resources and consumers. ECOWAS, the Economic Community of West African States, provides a framework for regional cooperation; however, nothing in the announcements reviewed supports presenting this network as a West African interconnection project.
For Senegal, the immediate challenge is to find partners and keep to the announced 2027-2029 timetable. Progress on the northern section, financing agreements and tariff terms will also need to be monitored. At regional level, the case illustrates a shared challenge: turning energy resources into a reliable supply without conflating new infrastructure with guaranteed lower bills or equitable access to electricity.
Background sources: presentation of the programme at African Energy Week, PETROSEN information on the RGS, RGS description of the northern section, RTS information on the September 2026 electricity disruptions.