For gas from northern Mozambique to power factories in the country, producing it is not enough. It must also be connected to consumers, access conditions must be set, and expected revenues must be turned into local activity. The revision of Rovuma LNG now puts these issues at the heart of the project.
A national rule applied to a major project
The Rovuma Basin, off the coast of Cabo Delgado province, is home to several gas projects intended in particular for export. Rovuma LNG concerns Area 4. It is operated by Mozambique Rovuma Venture, a joint venture between Eni, ExxonMobil and CNPC. At regional level, Mozambique is a member of SADC, the Southern African Development Community, where energy and cross-border infrastructure are major issues.
The country already produces gas at Pande and Temane, in the south. Industrial users and power stations are supplied there, particularly in Inhambane and Maputo provinces. But Rovuma gas is far from these networks. The National Petroleum Institute (INP) lists existing domestic uses and notes that new volumes from projects in the basin could expand domestic supply. The central question, therefore, is one of pipelines, processing facilities and buyers able to absorb the volumes.
Mozambique’s Petroleum Law, adopted in 2026, provides for a share of production to be allocated to the domestic market. The government is applying this policy to Rovuma LNG as Maputo seeks to link extractive investment more closely to industry, employment and public revenue.
Higher capacity, but timetable still to be confirmed
The Council of Ministers approved the amendment to the development plan on 17 November 2026. According to the INP and the Mozambique Local Content Office, planned annual capacity will rise from 15.2 to 18.6 million tonnes of liquefied natural gas (LNG), following a revision of the initial project approved in 2019.
The plan reserves 25% of the natural gas produced for the Mozambican market. This does not mean consumers will receive these volumes immediately. The concessionaires must develop delivery infrastructure. Gas intended for the domestic market is to be sold at production cost, under provisions made public by the authorities.
The revision also provides for electric modules to process the gas. The INP estimates that this configuration could cut emissions by about 40% compared with the initial plan and reduce development costs. This is an official estimate for the project; it is not, by itself, a measure of actual emissions during operations.
The project represents an announced investment of $26 billion during the production phase. The INP estimates that the state could receive $121 billion in financial gains over 25 years. This figure is a projection, not revenue already secured. It will depend in particular on the timetable, costs, selling prices and revenue-sharing arrangements.
Bringing more of Mozambique’s economy into the project
The amendment strengthens the role of the National Hydrocarbons Company (ENH), the state-owned company. It is to receive condensates from the project for marketing. The arrangement also provides for liquefied petroleum gas (LPG) to be supplied to ENH at production cost. According to information published on the resolution, the concessionaires would finance the state-owned company’s capital contribution, at an interest rate capped at 6% a year.
These mechanisms could support ENH’s capacity, but they do not automatically guarantee net revenue for the state. Financing its stake also creates a financial obligation that will need to be monitored. Transparency on costs, volumes delivered and marketing terms will be crucial in assessing the actual benefits.
The INP also projects $6 billion in potential contracts for goods and services for Mozambican companies. Operators will have to update their local content plans after construction and installation contracts are awarded. The programme also provides for training national workers and their gradual access to specialised positions.
For local companies, the challenge will be to meet the technical standards and schedules of a complex industrial project. For workers, the announced training will have lasting effects only if it leads to skilled jobs. The benefits will not be evenly distributed: suppliers able to compete for major contracts are not necessarily based in the communities near the facilities in Cabo Delgado.
Next steps will show whether gas becomes an accessible resource
The revised plan gives the partners six months after its approval to take a final investment decision. If they do not, they will have to present a new timetable, which may be extended by no more than a further three months. This deadline will show whether the announced capacity translates into an effective financial commitment.
SADC gives the issue regional significance: increased production could strengthen Mozambique’s position among southern African energy suppliers. But LNG exports and domestic supply involve different logistics chains. The former depends on liquefaction facilities and foreign markets; the latter on national networks, affordable tariffs and industries able to use the gas.
The example of Pande and Temane shows that local supply can power businesses, provided the infrastructure is in place. For Rovuma, the indicators to watch will therefore be the final investment decision, funding for pipelines, the implementation of local contracts and the publication of data on volumes actually delivered. These are the stages that will test the promise of gas as a resource for Mozambique’s economic development.