In Lualaba, work on a drainage structure could have consequences beyond the boundaries of a mining concession. If it is indeed changing flows around the Musonoi River, its effects could reach the Metalkol plant, the Nzilo power station and communities downstream. For now, the company has raised the alarm over a hydraulic risk, but no independent confirmation has been made public.
Warning over water flows around the Musonoi
On 3 October 2026, Metalkol reported that a drainage structure associated with Nzilo had allegedly been blocked in part of its concession, near Kolwezi, in Lualaba Province. According to an internal note reported by Bankable, operators at the site allegedly blocked the structure to prevent water from flooding the area they occupy.
Metalkol says the intervention would divert some of the water from the Musonoi basin towards the Kasubantu dam. The company fears a reduction in the volumes available to the reservoirs that supply hydroelectric power generation at Nzilo. It says it has alerted the Société nationale d’électricité (SNEL), which operates the Congolese electricity network, and plans to send it a formal notification.
The distinction matters: the blockage and its consequences are described on the basis of a note attributed to Metalkol. No independent flow measurements, or public response from SNEL confirming disruption at the power station, have been identified. It has therefore not been established that electricity generation has already fallen.
The report also cites a risk of flooding, in the event of heavy rain, for farmland downstream of the Kasubantu dam and the village of Port Lambert. Here too, this is a risk raised by the company, not damage that has been publicly documented.
A supply chain extending beyond the mine
Nzilo is one link in SNEL’s southern network, which serves Lualaba and Haut-Katanga, among other areas. The company lists the power station among the facilities supplying cities and mining activities in the south-east. Its installed capacity is often put at around 100 megawatts; Congolese documents cite 108 MW. These figures refer to theoretical capacity, not the amount of electricity actually generated at any given moment.
The dependence runs both ways. Metalkol needs electricity to process mine tailings, while hydroelectric generation depends on water management in a region where several uses coexist. A change in water flows could therefore complicate mining operations and, if significant enough, weaken a supply shared with other users of the southern network.
SNEL says the network is supplied by several power stations, including Nzilo, Nseke, Koni and Mwadingusha. This diversity may limit the impact of an isolated incident, but its effects cannot be measured without data on flows, reserves and available generation. For businesses, electricity constraints can disrupt operations. For households and small businesses, the consequences would depend on distribution decisions and the duration of any potential reduction.
Metalkol recovers copper and cobalt from old mine tailings. The company gives its annual nominal capacity as about 100,000 tonnes of copper and 23,000 tonnes of cobalt. According to the report, rising water levels are already affecting a storage area intended to secure supplies to the plant during the rainy season. However, no production cuts had been reported in the information available in early October.
Contested occupation amid local tensions
The hydraulic warning is part of a wider dispute over an area of the concession. Reports published by Mining & Business describe operators being present since February 2026, an eviction in May, and a new occupation reported in August. The same outlet reports that the Minister of Mines revoked the Hosanna cooperative’s permit on 10 August. These details describe the administrative context; on their own, they do not prove who blocked the hydraulic structure.
The outlet also reports allegations involving armed men in uniform, heavy equipment and mineral convoys. These claims remain attributed, and some are disputed. In an article published on 26 September, Congolese outlet Actualite.cd also reported an operation by the General Directorate of Migration targeting Chinese nationals suspected of illegally buying minerals at concessions in Lualaba, including Metalkol. The operation confirms the scrutiny of mining supply chains in the province, but does not resolve the allegations specific to the site occupation.
The case thus involves several interests that should not be conflated: the security of the industrial site, the activities of operators on the ground, revenue from minerals and the protection of neighbouring communities. Rural areas downstream may be exposed to changes in water levels, while workers and subcontractors depend on the continuity of operations. Checking the flow rates and clarifying responsibility are therefore essential before attributing specific consequences to the incident.
What the authorities and SNEL need to establish
The first step is to determine whether the structure is indeed blocked and measure the effects on flows in the Musonoi, the Kasubantu dam and Nzilo’s reserves. An assessment conducted with SNEL and the relevant water and mining authorities would help distinguish a potential risk from an actual disruption. It should also examine possible consequences for farmland and homes downstream, particularly during heavy rain.
SNEL confirms that Nzilo contributes to the southern network, but its public information provides no specific data on this incident. Nor have the Congolese authorities published, in the material reviewed, a technical report establishing the extent of the blockage or its effects. In the meantime, figures for threatened output and volumes of minerals removed must remain attributed to those making the claims.
At regional level, the issue is a reminder of how closely mining and electricity are linked in the Copperbelt, a cross-border copper and cobalt-producing basin shared notably by the DRC and Zambia. But the immediate challenge is in Lualaba: to preserve an electricity network serving cities and industries, ensure the safety of facilities, and prevent local communities from bearing the consequences of a land and operational dispute alone. What happens next will depend on technical findings and decisions by the Congolese authorities.