Ghana: Sankofa upgrade does not guarantee more gas for domestic market from 2028

Yinson and Eni plan to expand gas processing at Sankofa and raise the FPSO’s export capacity to 355 million cubic feet per day. But reservoir pressure and infrastructure will determine the volumes actually delivered to Ghana.

A technician inspects electrical equipment on a busy street in Accra, Ghana.

For Ghana, increasing the capacity of offshore equipment is not enough to guarantee more gas for power stations and factories. The challenge is twofold: maintaining Sankofa’s output despite the expected fall in reservoir pressure, then transporting and absorbing that production in a growing market.

A technical lever to address falling pressure

On 2 October 2026, Yinson Production and Eni agreed an amendment to the contract for the FPSO John Agyekum Kufuor, the floating production unit that processes hydrocarbons from the Offshore Cape Three Points (OCTP) project off Ghana. The agreement provides for the installation of new gas compression and processing equipment.

The vessel’s gas export capacity is expected to rise from around 210 to 220 million standard cubic feet per day to 355 million. Two modules are to be added: one with two gas turbine-driven compressors, and another dedicated to processing the additional volumes. Yinson expects the work to be completed in the first quarter of 2028. These details are set out in Yinson’s announcement on the FPSO capacity expansion, which was also reported by Ghanaian media.

The amendment extends the vessel’s firm charter period by four years, to 2036. The additional contract value is estimated at about $810 million, of which around $600 million is attributed to Yinson in information made public by the group. This contractual amount remunerates services related to the vessel, among other things; it is not, in itself, a measure of total investment in the field or a guarantee of revenue for the Ghanaian state.

One part of a wider gas system

Sankofa is part of OCTP, which also includes the Gye Nyame and Sankofa fields. The gas is transported to the receiving facilities at Sanzule, in the Western Region, before joining the national network. In operation since 2018, the project has become an important supplier to Ghana’s power sector and industry.

In July 2025, an upgrade to the facilities increased OCTP’s non-associated gas processing capacity from 246 to 270 million cubic feet per day, according to Eni and Ghanaian press reports. That same year, Eni said the project’s gas contributed about 34% of the country’s electricity generation. These figures describe capacity and a reported contribution at a given time, not a guaranteed continuous supply.

The new amendment addresses a different constraint: the anticipated decline in reservoir pressure. Compression can help bring gas to the surface and process it as natural pressure falls. It does not, however, create new reserves. The volumes actually delivered will also depend on the condition of the field, wells and onshore facilities, as well as maintenance operations.

Rising demand, but capacity and delivery are not the same

Ghana’s gas needs are being driven in particular by power generation and industrial activity. Ghana Gas projects national demand of 715 million cubic feet per day in 2030, up from about 502 million currently, according to figures cited in debate on gas infrastructure. The projection highlights the stakes, but does not mean all that demand will automatically be affordable or met by Sankofa.

The country relies on several sources: the offshore Jubilee and TEN fields, OCTP, and gas imports from Nigeria via the West African Gas Pipeline. The Ghana National Petroleum Corporation (GNPC), the national company and gas aggregator, plays a role in balancing available volumes with market needs. Ghana’s energy regulator also notes that scheduled shutdowns and supply constraints can cause shortfalls. The Ghana Energy Commission’s 2025 report details these risks linked to maintenance and fluctuations in supply.

The consequences of a gas shortage are not uniform. Thermal power stations may have to switch to liquid fuels, which are generally more expensive and push up electricity generation costs. Industrial businesses may also face interruptions or higher energy costs. For households, the impact may be felt through electricity reliability and tariffs, but is neither immediate nor automatic.

Conversely, increasing export capacity aboard the FPSO does not guarantee that the national network can transport or absorb the volumes. Onshore infrastructure, purchase agreements and the financial position of the power sector also matter. Ghana has already faced tensions linked to “take-or-pay” contracts: this clause requires the buyer to pay for an agreed volume even if it does not take the full amount. The precedent is a reminder that supply exceeding effective demand can also be costly for public finances.

A national and West African issue

For Accra, the project is part of a broader strategy: securing electricity, supporting industry and reducing vulnerability to supply disruptions. GNPC has also advocated an integrated approach bringing together production, processing, transport and contracts, rather than relying on a single field. The national company presents the resources of Jubilee, TEN and Sankofa as complementary components of energy security.

Regionally, Ghana is a member of the Economic Community of West African States (ECOWAS), which supports energy integration between countries. Nigerian gas transported through the West African Gas Pipeline already illustrates this interdependence. For Accra, domestic production from Sankofa can reduce exposure to external disruptions, but it does not replace regional trade or investment in networks.

The next concrete milestone is the first quarter of 2028, the target date for commissioning the new modules. Three outcomes will then need to be distinguished: the announced technical capacity, the volumes actually produced by the reservoir and the quantities effectively delivered to the Ghanaian market. It is this last measure, more than the capacity of the offshore equipment alone, that will show whether the project strengthens the country’s supply over the long term.