EACOP: how Uganda’s first oil could reshape trade with Tanzania

EACOP is due to begin filling in December 2026, ahead of a first cargo from Tanga in early 2027. The infrastructure gives Uganda an export route and strengthens Tanzania’s energy role.

East African delegation gathered in Tanga around the EACOP project, in a sober, contemporary institutional setting.

For Uganda, oil from the Lake Albert basin will not generate export revenue until it reaches the Tanzanian coast. The announced timetable for filling the EACOP pipeline brings that step closer, but several technical operations remain before the first vessel can depart.

A regional infrastructure project nearing completion

On 21 September 2026, Tanzania Petroleum Development Corporation (TPDC) managing director Mussa Makame said that filling the pipeline would begin in December 2026. The first crude cargo could then leave the Chongoleani terminal, near Tanga, in February or early March 2027.

The announcement sets a clear timeframe for a project that has faced several delays. TPDC attributes them to difficulties in delivering specialised equipment and spare parts. Disruptions to supply chains linked to conflicts in the Middle East have also affected the schedule.

According to the latest data released by EACOP, the pipeline was 92,7 % complete as at 31 August 2026. The figure was presented during a visit by Uganda’s Minister of Energy and Mineral Development, Monica Musenero Masanza, to the Kabaale pumping station in Hoima district.

The route runs for 1 443 kilometres between Hoima, in western Uganda, and the Chongoleani peninsula in the Tanga region. The buried, heated pipeline is designed to keep Ugandan crude flowing to the marine terminal, where the oil will be stored and then loaded onto vessels.

The project includes six pumping stations, two pressure-reduction stations and storage facilities in Tanga. Its nominal capacity is 246 000 barrels per day. It is intended to support the ramp-up of the Tilenga and Kingfisher fields, whose combined output is expected to reach around 230 000 barrels a day at full capacity.

Hoima and Tanga at the heart of oil strategy

EACOP addresses a geographic constraint first and foremost. Landlocked, Uganda has no direct access to the Indian Ocean. The new link will allow it to transport its crude to international markets via Tanzania, rather than relying on a road or rail corridor to a foreign port.

The fields in question are in the Albertine region, around Lake Albert. Tilenga is operated by TotalEnergies EP Uganda. Kingfisher is being developed by CNOOC Uganda. The two projects are at the heart of the production system set to supply the pipeline.

For Kampala, the stakes go beyond exports alone. Oil revenues are expected to contribute to public finances, infrastructure and the development of the local services sector. These effects, however, will depend on actual production levels, crude prices, the tax regime and the state’s ability to manage the revenues transparently.

Tanzania, for its part, is pursuing a strategy to establish Tanga as an energy and trade hub on the East African coast. The Chongoleani terminal is expected to generate transit revenue, support port services and strengthen industrial activity related to storage, maintenance and logistics.

The ownership structure reflects this bilateral cooperation. TotalEnergies holds 62 % of EACOP, CNOOC 8 %, while the Uganda National Oil Company and TPDC each own 15 %. The project is designed to operate for 25 years.

A delicate transition from construction to operations

The start of filling will not yet mean full commercial operations. The pipeline’s integrity will have to be checked, equipment tested and pressure stabilised, while operations are coordinated between the production facilities in Uganda and the marine terminal in Tanzania.

February 2027 is therefore an operational deadline, but remains subject to technical and logistical uncertainties. The TPDC managing director himself mentioned the possibility of a departure in early March. This leeway shows that the announced date should be treated as a target, not a definitive guarantee.

The project has already had economic effects along the corridor. Its promoters say that more than 12 000 people have been directly employed in Uganda and Tanzania, while more than 20 000 indirect jobs are reported to have been supported. TPDC, for its part, puts the number of Tanzanians employed on the project at around 7 500.

These estimates do not necessarily cover the same job categories. They should therefore be read with caution. The question now is how many positions will remain accessible to local workers during operations, when construction needs decline.

Community projects have also been announced along the route, including initiatives to improve access to water and roads. In both Uganda and Tanzania, their implementation will weigh in local assessments of the project. People affected by the pipeline’s route are above all waiting for effective compensation, restored livelihoods and sustained access to essential services.

EACOP says that 13 686 people affected by the project have received compensation in cash or in kind. Associations and researchers have nevertheless continued to document tensions related to land acquisition, restrictions on land use and environmental risks. These criticisms will not disappear with the first cargo.

A project followed across East Africa

EACOP forms part of the East African Community (EAC), a regional organisation that facilitates economic cooperation among its member states. The project brings Uganda and Tanzania together in a practical way around strategic infrastructure, as regional trade continues to seek lower transport costs and shorter delays in access to ports.

Its regional impact will nevertheless depend on how revenues are distributed. Uganda will benefit from access to exports. Tanzania will receive transit revenue and strengthen its maritime role. The areas along the route, meanwhile, will judge the project on the jobs, compensation and services actually available.

The next milestone to watch will be the start of filling in December 2026. Testing will follow, then the arrival of crude in Tanga and the first loading operation, announced for between February and early March 2027. The timetable’s success will therefore be measured not only by a vessel’s departure, but also by the two countries’ ability to turn this infrastructure into a lasting and accountable economic benefit.