Tunisia’s Gasaat projects strong returns, but financing and permits remain outstanding

PhosCo estimates Gasaat’s initial investment at $199 million and projects production over 49 years. Despite US interest, financing, permits and feasibility studies remain to be secured.

A Tunisian geologist’s hands sorting phosphate samples on a workbench in Kasserine.

A mining project can show high returns on paper without having secured financing, obtained permits or set a production timetable. That is the key caveat around Gasaat, a phosphate project led by Australian company PhosCo in central-western Tunisia.

The company now puts the initial investment required at US$199 million. This estimate marks a new stage of assessment. But it does not mean the mine is financed or that construction has begun.

A project still at the study stage

Gasaat is in Kasserine governorate, within the Northern Tunisian phosphate basin. The exploration permit covers 112 km². It includes the former Chaketma project, among other areas, according to information published by PhosCo on the Gasaat area. Tunisia’s Ministry of Energy and Mines also lists the Gasaat permit among mining titles, with sectors in Kasserine, Kef and Siliana.

The project forms part of a national trajectory in which phosphate already plays an important role. The Gafsa Phosphate Company and processing activities linked to the sector have long shaped the economies of several areas. Gasaat offers a new prospect for extraction, but its development will have to contend with infrastructure, water needs, environmental rules and the expected benefits for the regions concerned.

At regional level, Tunisia belongs to the Arab Maghreb Union (AMU), an organisation bringing together five North African countries. Trade and supply chains can also extend beyond this political framework. Phosphate fertilisers are a strategic raw material for agriculture in Tunisia and across African and international markets.

Ambitious projections, yet to be confirmed

PhosCo’s updated preliminary economic assessment forecasts production of 1.4 million tonnes of concentrate a year for 49 years. The previous estimate envisaged 1.5 million tonnes annually for 46 years, with an initial investment of US$169.5 million. The new scenario therefore slightly reduces projected annual production while extending the mine’s estimated life.

PhosCo also reports an after-tax net present value of US$732 million and an after-tax internal rate of return of 52%. The company estimates that the investment could be recouped 20 months after commercial production begins. These indicators are projections based on a preliminary study. They rely on assumptions about costs, prices and implementation that will need to be examined in greater depth before any final decision.

The next step is to conduct a pre-feasibility study, followed by a bankable feasibility study. This work must clarify technical choices, costs, required infrastructure and project risks. A preliminary economic assessment is not an investment decision, and the announced figures are no guarantee of profitability.

The administrative process will also be decisive. The title currently listed is an exploration permit. PhosCo will need to obtain the permits required for any potential exploitation, including a mining concession, as well as the applicable environmental approvals. Preparatory work will also assess the practical conditions for water supply and transporting the ore.

Washington is seeking partners, not yet a financed mine

On 29 October, the US embassy in Tunisia announced a two-year programme implemented with CrossBoundary, a company specialising in investment advisory services. The initiative aims to connect PhosCo with potential investors and buyers, with the goal of mobilising up to US$100 million in private capital for the project. Tunisian media reported the announcement, which reflects US interest in diversifying supplies of minerals and agricultural inputs.

The distinction is crucial: the US programme funds support intended to facilitate investment and commercial relationships. The available information does not indicate a direct payment of US$100 million to PhosCo, a firm purchase agreement or a confirmed commitment from the US International Development Finance Corporation (DFC). The amount sought remains a target, not secured financing.

At the same time, PhosCo is counting on a facility linked to the European Bank for Reconstruction and Development (EBRD) to support the studies. The A$7.5 million mentioned by the company represents funding under consideration subject to conditions, not a sum already paid in full. The bank must still complete its due diligence and approval procedures.

Local benefits will be decisive

For Tunisia’s authorities, the challenge is to turn an exploration permit into productive activity without reducing the project’s assessment to its financial forecasts alone. Job creation, the share of work awarded to Tunisian companies, training and public revenues will all weigh in the assessment. The impact will not necessarily be the same for Kasserine residents, businesses based in major urban centres and players in the national mining sector.

Water needs and logistics are among the issues to be clarified as the studies progress. Concentrate transport, required infrastructure and competing uses of water could have direct consequences for local areas. At this stage, these matters call for detailed assessments and public decisions; they do not allow the project’s effects to be determined in advance.

An earlier PhosCo study referred to a railway line near the permit, but the existence of infrastructure in the region is not enough to establish that its use would be technically and economically suitable for Gasaat. The route selected, transport costs and equipment requirements will have to be confirmed in future studies.

Gasaat is attracting foreign counterparts, while Tunisian engineering partner STUDI announced a partnership with PhosCo in October. This local presence could help anchor studies and expertise in the country. It does not, however, replace permits, the actual raising of capital or consultation with the areas concerned.

The next test: moving from announcements to decisions

Tunisian phosphate could strengthen the diversification of fertiliser supplies, but Gasaat remains at the preparation stage. The next milestones will be pre-feasibility, bankable feasibility, permits and confirmation of financing. The industrial timetable will depend on these steps, as well as any commercial agreements.

For Tunisia and its North African neighbours, the case illustrates broader competition over resources that supply agriculture and industrial value chains. Gasaat’s significance will be measured less by capital announcements than by whether they materialise, the benefits actually shared and the ability to reconcile extraction with local needs and environmental requirements.

Sources consulted: PhosCo’s presentation of the Gasaat project ; official Tunisian list of mining exploration permits ; La Presse report on the US programme ; Tunisian reporting on the updated study and project stages.