Togo plans 120 MW dispatchable power plant in Lomé

Togo is preparing a 120 MW dual-fuel thermal power plant in Lomé to meet peak demand of 360 MW and annual growth of 10%. Backed by the World Bank, the project aims to strengthen grid stability.

In a newsroom in Lomé, journalists prepare a report on energy, with microphones, blurred screens and anonymous documents.

In Lomé, electricity is no longer simply a matter of comfort. It is essential to continuity for households, productivity for workshops and reliability for the services that keep the city running. When demand grows faster than supply, every megawatt counts, especially in a country seeking to industrialise, expand access and stabilise its grid at the same time. The new dual-fuel power plant project in Lomé is designed to address precisely this challenge.

A response to a structural electricity shortfall

Togo has put energy at the heart of its economic strategy. Under the National Energy Compact, adopted as part of the Mission 300 initiative, the Togolese authorities are aiming for universal access to electricity by 2030. This continental initiative, led by the World Bank and the African Development Bank, aims to connect 300 million Africans to reliable electricity by 2030.

Against this backdrop, the ministry responsible for energy has announced a 120 MW dual-fuel thermal power plant at the Lomé Thermal Power Plant site. A consultation meeting with operators is scheduled for Friday, 18 September 2026, in Lomé. The company is expected to be selected in the fourth quarter of 2026. The project is receiving financial support from the World Bank and forms part of a broader effort to strengthen Togo’s electricity system.

The choice of site is no coincidence. The Lomé Thermal Power Plant is already operating and is a key node in the national grid. The new project is therefore intended not so much to create infrastructure from scratch as to bolster an existing strategic link in a capital where demand is high and a stable power supply is vital to daily economic activity.

What the project entails

Official documents describe a modular power plant equipped with dual-fuel engine units. It will initially run on natural gas, with the option of using liquid fuel as a supplementary source. This dual-fuel design offers a straightforward advantage: if gas supplies become constrained, the plant can temporarily switch to another fuel. In other words, Togo is seeking operational flexibility, not just installed capacity.

The contract covers design, supply, installation, testing, commissioning, staff training and maintenance after provisional acceptance. Connection to the 161 kV transmission grid is planned. Site preparation and the environmental and social impact assessment are the responsibility of the project owner. These details show that this is not merely an announcement of new capacity, but a complete technical and institutional process.

The authorities have also cited a key figure: peak electricity consumption reached 360 MW in the first quarter of 2026, with growth estimated at about 10% a year. The new 120 MW unit is therefore intended to serve as a dispatchable reserve when the grid is under pressure, particularly at peak times and during periods of heavy demand.

This figure helps explain the choice of technology. For now, Togo is not relying on a single solution. It is combining grid expansion, increased generation and greater flexibility. The World Bank, for its part, is framing its support around reliability first, followed by financial sustainability.

Why Lomé faces so much at stake

The Togolese capital is home to the country’s administrative life, a large share of its commercial activity, and businesses linked to the port, logistics and services. In this context, a prolonged power cut quickly becomes costly. It disrupts small and medium-sized enterprises, complicates the storage of goods, drives up diesel self-generation costs and undermines the competitiveness of formal businesses as well as incomes in the informal sector.

The social context also shows why electricity remains an issue of territorial equity. The World Bank notes that poverty is much higher in rural than urban areas in Togo, at 58.8% compared with 26.5%. It also points to marked disparities in access to basic services between towns and the countryside. In the energy sector, a World Bank diagnostic report notes that access to electricity has increased, but with major differences between urban and rural areas: 96% access in urban areas compared with 24.7% in rural areas in 2021, according to the report.

The power plant project will not solve everything. Its first purpose is to meet the need for dispatchable capacity—that is, generation that can be brought online on demand. But it must also go hand in hand with grid expansion, lower connection costs and improved distribution. Without these measures, more generation capacity does not automatically mean more households receiving a reliable supply over the long term.

The Togolese authorities say they are pursuing a broader trajectory. The government aims to achieve an electrification rate of 90% in 2028, followed by universal access in 2030, according to a World Bank document linked to the country’s energy compact. This ambition puts energy at the centre of Togo’s economic compact: more electricity to support greater production, but also greater reliability for public services and households.

Regional context and continental significance

The project extends beyond Togo. It is part of a wider West African drive towards regional electricity integration, in which ECOWAS is playing a role. The $160 million in financing approved by the World Bank in June 2026 for Togo and The Gambia is also part of a broader regional programme, the West Africa Regional Electricity Market Program, led in partnership with ECOWAS.

Across Africa, the signal is clear. Governments are now seeking hybrid approaches: flexible thermal generation to secure the system in the short term, the expansion of renewables and reforms to attract the private sector. Mission 300 provides a continental framework for this push. Togo is emerging as a test case, seeking to combine universal access targets, multilateral support and practical solutions to sustain the urban economy and serve areas that remain poorly covered.

One date remains to watch: the consultation with market participants in Lomé on 18 September 2026, followed by the selection of the operator in the fourth quarter of 2026. That will be when the project moves from intentions to technical, financial and industrial decisions. Togo’s challenge is straightforward: to turn announced capacity into a service that is operational, reliable and sustainable.