In several communities in central Nigeria, the challenge is no longer just generating electricity. Equipment must also be financed before the first revenues and public grants are paid. That is precisely the role of the new financing structure mobilised around Prado Power.
Hybrid financing to accelerate access to electricity
The Nigerian developer plans to build and operate five solar mini-grids in Benue and Nasarawa states. The installations are expected to have a total capacity of 1.84 megawatt-peak and 5.2 megawatt-hours of battery storage.
More than 12,000 connections are planned. They will serve households, small shops and businesses in areas that remain poorly connected to the national electricity grid.
The financing includes senior debt from REPP 2, a private fund specialising in renewable energy infrastructure and managed by Camco. The announcement was made on 30 September 2026.
Senior debt is a loan that is repaid ahead of other claims. For a developer, it makes it possible to start construction, buy panels and batteries, and bring sites into service before receiving all the expected grants.
The five projects are part of the DARES programme, an acronym for Distributed Access through Renewable Energy Scale-up. The $750 million initiative, funded by the World Bank and implemented in Nigeria by the Rural Electrification Agency, aims to improve access to electricity for 17.5 million people.
The programme includes the deployment of 1,225 mini-grids, as well as the installation of standalone solar solutions for households and small businesses. It prioritises communities where extending the main grid remains difficult or too costly.
The decisive role of grants paid after results are achieved
Under the model adopted by DARES, public support is not paid in full at the start of a project. Part of it depends on connections actually being made and installations operating.
For isolated mini-grids, performance-based grants are calculated according to the number of new customers connected. This mechanism aims to prevent public funds from financing equipment without actual users.
In the case presented for Prado Power, 80% of the grant would be paid after the infrastructure enters service, based on the connections made. The balance would depend in particular on reaching a minimum level of consumption. These terms are intended to encourage operators to keep the equipment running and develop productive uses of electricity.
This schedule nevertheless creates a significant cash-flow requirement. The company must incur a large share of the costs before receiving all the public support. Debt therefore helps bridge the temporary gap between investment and results-based disbursements.
This type of financing combines several sources of capital. Public authorities reduce the initial cost and risk through grants. Private lenders provide the funds needed for construction. Operators, for their part, bear technical and commercial responsibility for the sites.
Camco describes this financing as support for the expansion of decentralised energy infrastructure in Africa. Prado Power had already used this model before the latest deal.
Prado Power scales up
In March 2026, the International Finance Corporation, a member of the World Bank Group, signed a financing facility of up to $10 million with Prado Power. Norfund, the Norwegian investment fund for developing countries, is also participating in the arrangement.
According to information published by the International Finance Corporation, the facility is intended to help Prado Power finance up to 41 mini-grids. The company is targeting nearly 49,500 new connections, with total investment costs estimated at $33.3 million.
The financing combines a senior loan from the International Finance Corporation, a parallel loan from Norfund and concessional subordinated debt. The latter has more favourable terms than a conventional commercial loan and improves the operator’s ability to mobilise other capital.
The projects concerned are also expected to benefit from performance-based grants under the DARES programme. The mechanism provides in particular for future grants to be allocated to debt repayment. In practice, the lender relies on expected public revenues that are conditional on results being delivered.
The International Finance Corporation says Prado Power develops hybrid mini-grids combining solar generation and storage. The company is also seeking to link access to electricity with the needs of farms, small businesses and local economic activities.
A national challenge extending beyond rural areas
For Nigeria, mini-grids are not a marginal solution. They address the difficulty of quickly supplying electricity to a large, populous country marked by wide disparities between states.
In rural areas, a more reliable electricity supply can extend workshop operating hours, support the preservation of agricultural produce and reduce the use of generators. In small towns, it can also strengthen health services, shops and digital activities.
However, the effects will not be the same for all users. Households must be able to afford basic consumption. Businesses will need tariffs compatible with their margins. Operators, meanwhile, will have to maintain batteries, provide after-sales service and meet the consumption levels set out in contracts.
Success will therefore depend as much on the construction of installations as on their long-term operation. The number of connections alone will not be enough to measure the real impact. Service quality, outage duration, tariffs and economic uses will also be decisive.
ECOWAS watches a model that could be replicated
The Nigerian scheme is part of a broader discussion in West Africa. ECOWAS, which brings together countries in the region and works to integrate their markets, has for several years sought to improve electricity trade and access to renewable energy.
Mini-grids can complement large interconnected projects. They do not replace national grids, but make it possible to serve remote communities more quickly. Their development nevertheless depends on clear rules, suitable financing and coordination between the federal government, state governments, local authorities and operators.
The main point to watch will be Prado Power’s and other developers’ ability to turn financing pledges into operational installations. The regularity of DARES disbursements and the strength of repayment mechanisms will also need to be assessed.
If this model proves viable, Nigeria could attract more capital into decentralised energy infrastructure. For other ECOWAS countries, the experience will offer a concrete example of how to combine private debt, public grants and verifiable results.