Private PPAs drive South Africa’s new solar and wind farms

Private power purchase agreements are overtaking public tenders in South Africa. Backed by industrial firms, they are accelerating solar and wind projects, but the grid remains a brake on deployment.

Regional summit table in South Africa with documents, headphones and discreet small table flags.

As the private sector steps in, the grid must keep pace

In South Africa, the electricity transition is no longer playing out solely through public tenders. It is also being negotiated in the accounts of industrial groups, power producers and electricity traders. This is a significant shift for a country where power cuts have weighed on business activity, supply chains and investor confidence.

The signal is clear: large private power purchase agreements, often called PPAs, are gaining ground. Under the wheeling model, electricity generated at a distance travels over the grid to the end user. This allows companies to secure renewable energy without relying solely on public mechanisms. In South Africa, this shift is part of the reform launched in 2021 and then accelerated by the removal of the licensing threshold for private generation.

A reform born of crisis, now shaping the sector

The South African government first raised the licensing threshold for embedded generation from 1 MW to 100 MW in June 2021, before announcing in July 2022 the complete removal of the threshold for embedded generation projects. At the end of 2022, Parliament noted that the change had already brought forward more than 130 private projects, representing over 22,500 MW. The political message was simple: accelerate new capacity without relying exclusively on public procurement.

The shift also has an institutional dimension. Pretoria established a one-stop shop for energy projects in 2023, then, in 2025, an independent transmission programme to attract private capital into the power lines themselves. The Department of Electricity and Energy now says more than 14,000 kilometres of new lines will be needed by 2032, with the existing grid considered too slow to absorb the full potential of solar and wind power. In other words, producing more is not enough if electricity cannot flow.

Faster contracts, more complex projects

Recent examples illustrate the scale of the shift. In February 2026, SOLA Group reached financial close on Naos-1, a hybrid project combining 300 MW of solar power with 660 MWh of storage, intended for Sasol and Air Liquide. In the same month, the Orkney project, developed by Mulilo, reached financial close at around 219 MWdc in South Africa, with a power purchase agreement signed with Etana Energy as the sole buyer. These deals show that large companies are no longer looking only for green electricity: they want power that is available, integrated into the grid and contracted over the long term.

This growth confirms a trend already visible in South Africa’s private sector. Players such as Etana Energy now present diversified generation portfolios, including solar, wind and wheeling through national and municipal grids. Under this model, the producer develops the project, the trader aggregates demand and the consuming company secures its supply. For industrial firms, it is a competitiveness tool. For developers, it is a way to move beyond the timetable of public procurement alone.

The sticking point remains the same: grid connections. Eskom says the system’s recent stability does not remove its structural weaknesses, particularly in electricity transmission. The state-owned group also warns that delays to new generation capacity could create fresh pressure by 2029–2030. In this context, the challenge is not simply to add megawatts, but to align generation, transmission, storage and permits.

What this shift means for South Africa’s economy and the region

For large companies, the benefits are tangible: less exposure to power cuts, greater cost certainty and a clearer decarbonisation pathway. For the state, the task is more delicate. It must preserve the coherence of the system, prevent only the largest consumers from securing the best connections and maintain progress towards electrifying households that still lack reliable access. The department acknowledges that more than 1.6 million households remain affected by energy poverty.

The contrast between the formal economy and underserved areas is stark. Large industrial customers can sign contracts, finance projects and consume power quickly. Households in provinces with large backlogs, by contrast, depend on a grid that is slower to expand and on public investment that remains substantial. South Africa is therefore moving along two tracks at once: a growing private market and an unfinished public-service mission. The social credibility of the transition depends on this.

Across Southern Africa, this shift extends beyond South Africa’s borders. The country remains the largest economy in the SADC and a hub for electricity transit in several regional projects. If Pretoria can combine private PPAs, stronger transmission and clearer rules, the model could inspire other markets in the region. Conversely, if transmission lines are lacking, the risk is that a wealth of projects on paper will coexist with too little capacity actually connected to the grid. This point of friction warrants close attention in the coming months, as the private transmission programme and major industrial contracts move from announcement to implementation.