Off Mayumba, an accident during the installation of a drilling rig has interrupted some oil operations at the Dussafu licence. The sinking of the Prospector 5 has also brought an immediate question to the fore: finding the missing people and establishing precisely how the tragedy occurred.
Search efforts continue off Mayumba
The Prospector 5 sank on Saturday 24 October 2026, at around 20:37, as it was preparing for an offshore drilling campaign at the Dussafu Marin licence, off Nyanga province. The jack-up rig belonged to Borr Drilling, which was operating it on behalf of BW Energy.
Initial statements from BW Energy and the Gabonese authorities said there were 115 people on board. One hundred and ten were found safe. On 26 October, Gabon’s Ministry of Petroleum and Gas said five people remained missing. Reuters reported, citing three sources familiar with the matter, that an Indian worker had been found dead and four other people remained unaccounted for. The figure had not been confirmed by the Gabonese government in its latest available statement.
Borr Drilling has provisionally cited a loss of support during a preloading operation, followed by a loss of stability and the sinking. This is not an investigation finding. The Gabonese authorities have announced a technical investigation to determine the circumstances of the accident.
A crisis unit brings together the ministry, the navy, the National Agency for National Parks, Gabon Oil Company, BW Energy and Borr Drilling, among others. Search efforts and support for those rescued remain the priorities. According to the ministry, no harmful substance spill had been detected as of the date of its statement, 25 October. The area was nevertheless to remain under surveillance.
Drilling campaign halted before it began
The Prospector 5 was due to support the second phase of MaBoMo’s development, a production facility at the Dussafu licence. The programme called for four additional production wells, followed by a fifth well in the area known as 10P2. Initial production from each new well was forecast at around 5,000 barrels per day. These forecasts do not mean that the volumes will be achieved: they will depend, among other things, on the restart schedule and drilling results.
BW Energy said MaBoMo production had been shut down in accordance with procedures applied during preparations for drilling operations. The company reported no damage to the facility and no spill from it. It has not announced a new date for the campaign. The stoppage therefore affects one specific facility at the licence and does not mean that all Gabonese oil production has been suspended.
Dussafu is among BW Energy’s important assets in Gabon. In the third quarter of 2026, the licence supplied the company with 16,800 barrels per day net, out of total production of 21,500 barrels per day net across all its operations, according to figures released by the group. BW Energy holds 73.5% of the licence and is its operator. Panoro Energy owns 17.5% and national company Gabon Oil Company holds 9%.
MaBoMo’s oil is transported by pipeline to the BW Adolo, a floating vessel that processes and stores the crude before loading it for export. This arrangement links offshore operations to oil-sector revenues. The immediate effects of the shutdown will depend on how long it lasts and on the options available to keep the other fields operating. The workers affected by the sinking and their families, however, face an emergency distinct from production concerns.
Dussafu, a long-term project for Gabon
The drilling schedule was part of a phased development strategy. In 2025, BW Energy announced a discovery at the Bourdon prospect, also within the licence. The development project envisages several wells and a potential start to production around 2028. In 2026, the Gabonese authorities approved an extension of the licence to 2053. This gives the partners more time to exploit the resources, but does not guarantee the investment schedule or its returns.
The sinking therefore comes as the operator was preparing new drilling and Gabon was seeking to extend the life of its offshore assets. For the state and Gabon Oil Company, the licence involves revenues, national participation and operational safety. For BW Energy and Panoro, the delay could push back expected volumes. For offshore crews and coastal communities, the immediate concerns are the safety of people and protection of the marine environment.
The case also falls within the regional framework of CEMAC, the Economic and Monetary Community of Central Africa, of which Gabon is a member. Oil remains a strategic sector for Gabonese public finances and trade across the sub-region. But the accident alone is not enough to measure its effect on regional supplies: the duration of the shutdown and production trends across the whole licence will need to be established.
What happens next will depend on two concrete milestones: developments in the search and publication of the first findings of the technical investigation. Until that information is available, the death toll must remain attributed and the causes of the sinking presented as provisional. BW Energy has yet to say when MaBoMo can restart or when a new rig will be mobilised to resume drilling.