When energy becomes a matter of everyday sovereignty
In Cotonou, Lomé and Abidjan, the debate over gas is no longer confined to engineers. It now affects electricity bills, the stability of thermal power plants and states’ ability to secure supplies for their cities, ports and industrial zones. In this part of West Africa, the question has become easier to frame but harder to solve: how can countries move away from excessive dependence on a single source without abandoning regional integration?
The question comes as West African states seek to strengthen their energy interconnections. ECOWAS has long championed the idea of a regional gas market, and the West African Gas Pipeline, conceived in the late 1990s, embodied that ambition. But experience has also revealed its limits: when one link weakens, the whole system suffers. The power cuts and supply tensions observed in Togo in recent years are a reminder that a regional energy architecture is only as strong as its foundations in several supply sources, rather than one dominant supplier.
From the Nigerian corridor to a network approach
The West African Gas Pipeline was signed by Benin, Ghana, Nigeria and Togo in 1995, then governed by an intergovernmental agreement in 2000. Gas reached Ghana in 2008, and commercial operations were set to begin on 1 March 2011. For more than a decade, the corridor shaped supplies to several thermal power plants in the sub-region. It also established a clear dependence: when Nigerian production or transport slows, importing countries feel the impact immediately.
In April 2024, the Togolese authorities themselves explained that major works on natural gas production facilities in Nigeria had reduced the volumes destined for Togo, Benin and Ghana. The Togolese energy ministry linked the supply tensions to power cuts and the use of alternative fuels. In other words, this is not an abstract issue: it directly affects the cost of electricity generation and the stability of the grid.
It is against this backdrop that PRIME-GAS is taking shape. World Bank preparatory documents show that the project targets Côte d’Ivoire, Togo and Benin, with three specific objectives: to prepare short-term supply solutions, invest in national and regional gas infrastructure, and strengthen institutional capacity across the gas value chain and regional trade. A Beninese document from May 2026 also refers to virtual pipeline options, such as barges or trucks, from the port of Abidjan to Lomé and Cotonou.
Côte d’Ivoire takes on a new role
The shift is particularly visible in Côte d’Ivoire. Abidjan is no longer merely a potential consumer of regional gas. The country also wants to become a producer and redistribution hub. In May 2026, Ivorian authorities confirmed that the third phase of the Baleine field, developed by Eni, Petroci and Vitol, is expected to further strengthen the role of gas in the national energy strategy. In Washington in April 2026, the Ivorian minister of mines, petroleum and energy also described natural gas as a pillar of the country’s energy sovereignty.
This development is changing the geography of the project. Benin and Togo are primarily seeking to secure regular volumes to supply their power plants and reduce the vulnerability of their electricity systems. Côte d’Ivoire, by contrast, already has a production base and a port capable of supporting a more ambitious regional logistics network. PRIME-GAS is therefore not bringing together three identical situations. It combines three different but complementary interests: importing, securing and redistributing gas.
Past national efforts show why this collective approach is gaining ground. In Côte d’Ivoire, a regasification terminal at Vridi was announced in 2017, but did not progress to publicly operational service. In Benin, a 2019 agreement provided for a floating import and regasification terminal, intended in particular for the Maria Gléta power plant. In Togo, cooperation launched in 2018 with Equatorial Guinea was supposed to deliver the LNG2Africa project. None of these plans alone proved sufficient to produce a lasting solution.
What PRIME-GAS could change in practice
The project’s appeal is, first and foremost, financial. Three relatively small markets are unlikely, each on its own, to recoup the cost of LNG terminals, regasification units, storage facilities and transport links. By pooling demand, the states hope to improve their bargaining power with international suppliers and make their projects more bankable for private investors. The World Bank also classifies the project as environmentally and socially sensitive, showing that this is not merely an administrative exercise but major infrastructure with impacts that must be anticipated.
The stakes are also industrial. A more stable gas supply can secure thermal power plants, smooth generation costs and reduce reliance on more expensive fuels. For governments, this could limit the frequency of power cuts. For households and small businesses, it could primarily reduce the disruptions that penalise workshops, shops, services and urban transport. For industry, gas remains a factor in competitiveness, particularly in port areas and manufacturing hubs.
The project also raises questions of governance. A regional gas chain requires clear rules among states, regulators, operators and communities affected by pipeline routes. Public consultations and impact assessments mentioned in the preparatory documents will therefore be decisive. Without a transparent framework, pooling resources can quickly become a source of deadlock. With a credible framework, it could instead become a more tangible instrument of West African integration than many summit declarations.
A regional development to watch closely
At continental level, PRIME-GAS reflects a broader trend: several African countries no longer want simply to import energy; they want to organise regional value chains. This applies here to ECOWAS, but the signal extends beyond it. Gas, long considered country by country, is now being treated as an asset for cooperation. Côte d’Ivoire, Benin and Togo are testing a simple idea: energy security is better built together than in isolation.
What happens next will depend on the completion of studies, investment decisions and the implementation timetable. Public documents published in April and May 2026 show that preparations have entered a concrete phase. The challenge now is to turn the proposed architecture into infrastructure that is actually connected, capable of supplying the markets concerned over the long term and strengthening a West African energy corridor less vulnerable to shocks from neighbouring Nigeria.