In Freetown, NANT plant highlights energy challenge: generation and grid connections

The planned NANT plant in Kissy is expected to add more than 100 MW to Sierra Leone’s grid. But its impact also depends on EDSA’s work on the Blackhall Road-Ropoti line, which is crucial to absorbing the new output.

A low-key official group in an institutional room in Freetown, in connection with the electricity sector.

In Freetown, electricity is about continuity, not just generation

In eastern Freetown, an energy construction site says much more than a line of concrete, steel and cables. It speaks to the fragility of a grid still trying to make up for years of underinvestment, but also to the determination of Sierra Leoneans to make electricity a driver of work, industry and public services. The planned NANT plant in Kissy is part of this effort to secure a more stable power supply, at a time when outages and grid losses continue to weigh on economic life.

The issue extends beyond the capital. Sierra Leone is a member of ECOWAS, the Economic Community of West African States, and its regional energy system, the West African Power Pool, which organises the interconnection of West African grids. In this context, the country is seeking to move beyond a model in which available capacity remains below installed capacity and distribution often becomes the real bottleneck.

A private project backed by international and regional financing

The NANT plant is being developed by CECA SL Generation. According to financing documents, the project reached financial close in November 2024. The announced financing package comprises $292 million in debt from the U.S. International Development Finance Corporation, $40 million from the ECOWAS Bank for Investment and Development, and $85 million in equity from TCQ Power and Anergi. The funds are to finance a combined-cycle plant in Kissy, in eastern Freetown.

The project did not emerge from nowhere. In June 2024, the authorities had already presented the gas-fired plant project at Kissy Dockyard as the first major private initiative to generate electricity for the national grid. In government communications and technical documents, capacity varies slightly, between 105 MW, 108.4 MW and 108.5 MW. This difference reflects capacity updates as the project was being put together, but the overall scale remains a major addition to Sierra Leone’s system.

The construction work has implications for the grid beyond generation itself. The Electricity Distribution and Supply Authority (EDSA), the operator responsible for electricity distribution and sales, has begun work on the 33 kV Blackhall Road-Ropoti sub-transmission line, which crosses the project site. The line is to be rerouted and then buried before serving as a permanent link between the two substations. This may seem like a technical detail. In reality, it is crucial to integrating a new plant into an urban grid already under strain without disruption.

What NANT means for a system still short of power

Sierra Leone’s national energy compact sets out a simple fact: the country has about 271 MW of installed capacity, but just over 140 MW is actually available in the system. This gap between nominal and usable capacity explains why an addition of more than 100 MW could have such a significant impact. NANT alone would represent a substantial increase in usable supply, provided transmission and distribution can keep pace.

The government has placed the project within a broader trajectory. Under Mission 300, the initiative launched with development partners to accelerate access to electricity in Africa, Sierra Leone’s authorities aim to raise national coverage from 36% to 78% by 2030, while increasing installed capacity to 1.12 GW. The plan is ambitious. It targets urban households as well as small businesses, public services and rural areas, which are often served irregularly.

For Freetown’s residents, the stakes are tangible. More abundant generation is not enough if cables, substations and maintenance do not hold up. In the capital and secondary cities alike, unreliable electricity raises business costs, forces households to turn to generators and undermines small services that operate on a day-to-day basis. For businesses, the stakes are even clearer: a more reliable grid reduces losses, safeguards investment and makes operations more predictable.

The timeline matters too. The first delivery of electricity is scheduled for the third quarter of 2027. Until then, success will not be judged solely by the civil engineering work. It will depend on the ability of the state, EDSA and investors to coordinate construction, secure rights of way and prevent a new asset from running up against a grid too weak to absorb its output. This is often where African power projects gain or lose their real value.

A West African reach beyond Kissy

The Sierra Leonean case also matters at the regional level. The West African Power Pool, ECOWAS’s technical arm for grid integration, is working to facilitate electricity exchanges between member countries. Sierra Leone already participates through subregional interconnections, notably with Guinea, Liberia and Côte d’Ivoire. Within this framework, every new reliable generation unit strengthens national room for manoeuvre and, in time, regional integration.

This momentum carries greater weight as the region seeks to make energy a foundation for industry. The country is already exposed to reliance on imports and emergency supply agreements, while larger neighbouring economies are also seeking to stabilise their systems. Increasing capacity in Freetown will not eliminate this dependence, but it could reduce it and provide a stronger basis for integrating the West African electricity market.

What happens next will therefore depend on three things at once: construction of the plant, modernisation of the grid from Blackhall Road to Ropoti, and delivery of the national electricity access timetable. For Sierra Leoneans, the issue is not simply to generate more power. It is to get that energy to where it is needed, at the right cost and without interruption. Only then will the NANT project amount to a transformation, rather than merely an addition of megawatts on paper.

Automatic translation. Original French version