At Ferké, in northern Côte d’Ivoire, the estimated size of the gold deposit is growing faster than the timetable for a potential mine. The new data lend weight to the project, but guarantee neither its profitability nor its construction. Between exploration and production, several technical, economic and public decisions remain to be made.
A project still at the study stage
The project is located in a region where gold already plays an increasingly important role in the Ivorian economy. Nationally, production rose from 41.9 tonnes in 2021 to 59.1 tonnes in 2024, according to the assessment in the 2026–2030 National Development Plan. The authorities are targeting further growth, driven in particular by the opening of new sites.
This trajectory is part of a West African mining sector in which governments are seeking to attract investment while increasing local benefits. Côte d’Ivoire is a member of ECOWAS, the Economic Community of West African States. But decisions on permits, public revenues and communities living near sites are primarily the responsibility of Ivorian institutions and the national mining framework.
Ferké remains an exploration project, owned by Australia’s Many Peaks Minerals. Its main identified deposit to date is Ouarigue. In April 2026, the company announced an initial estimate of 1.323 million ounces, or about 41 tonnes of gold contained in measured, indicated and inferred resources.
Growth comes mainly from deeper resources
On 5 November 2026, Many Peaks published an interim estimate of 2.077 million ounces at an average grade of 1.87 grams per tonne. This represents about 64.6 tonnes of contained gold and an increase of 57% compared with the April estimate. The calculation is based on 34.6 million tonnes of ore.
The announced increase does not mean that this quantity can be extracted and sold. A mineral resource is a geological estimate. It becomes a reserve only if studies show that part of it can be mined in a technically and economically viable way, taking into account costs, infrastructure and environmental constraints, among other factors.
According to the company, the increase comes mainly from incorporating underground resources beneath the area being considered for open-pit mining. The new inventory adds about 754,000 ounces to the April estimate. This growth strengthens the site’s geological appeal, but also raises a practical question: what mining methods could recover the metal, and at what cost?
The company plans to complete an initial preliminary economic assessment by the end of 2026. A more in-depth feasibility study is planned for 2027. It is intended to examine technical and economic options and help determine whether a construction decision can be made in early 2028. These deadlines remain company targets, not decisions that have already been made.
Future benefits will depend on decisions still to come
The comparison made by Many Peaks chief executive Travis Schwertfeger with the Ivorian Bonikro mine concerns the deposit’s geometry and the possibility of an open-pit start. It is the company’s argument for explaining the project’s potential. On its own, it does not prove that Ferké will achieve the same results or that its resources will be converted into reserves.
For the authorities, a project of this size could contribute to mining activity and national revenues if it clears the necessary stages. For people living near the site, the issues are more immediate: access to jobs, purchases from local businesses, access to land and water, compensation and impact monitoring. The creation of a mine does not automatically guarantee an equitable distribution of its benefits.
The forthcoming assessment of the project will therefore also need to examine the conditions under which it would be developed. Water management, mine waste, site rehabilitation and local consultations are among the issues to be documented before any decision. The announced studies will help clarify some parameters, but the information currently available does not yet detail these findings for Ferké.
The increase in resources is part of the broader expansion of Ivorian gold production. The National Development Plan reports production of 59.1 tonnes in 2024, while sector forecasts put it at 61 tonnes in 2025 and 63 tonnes in 2026. These figures are not of the same kind: the first describes recorded production, while the others are forecasts. They should not be confused with longer-term production targets.
The next steps will be decisive
In the short term, the first milestone will be publication of the preliminary economic assessment. It should help evaluate costs and mining scenarios, without replacing the feasibility study. The possible conversion of some resources into reserves, permits, financing and environmental measures will then weigh on the timetable.
Ferké thus illustrates an important shift in Côte d’Ivoire’s mining sector: the challenge is no longer simply to discover deposits, but to turn estimates into viable projects and manage the benefits they generate. The announced increase is a geological milestone. For people in the region and the national economy, the central question remains the conditions under which a mine could be developed.