The Gambia expands national grid to narrow rural electricity gap

The Gambia is investing $14.2 million to connect 241 rural communities. But the country must also increase generation and develop renewables to ensure reliable service.

Regional meeting in Banjul on extending The Gambia’s electricity grid, with documents and translation headsets

In rural areas of The Gambia, access to electricity is no longer an issue confined to the big cities. It now depends on the state’s ability to extend power lines to remote communities while ensuring sufficient and affordable generation.

The Gambian government has taken a further step in this strategy. Two public contracts, worth a total of about $14.2 million, are set to connect 241 communities in the Central River and Upper River regions. The aim is to narrow the gap between the capital, Banjul, urban areas in the west and the country’s interior.

A choice suited to Gambian geography

The Gambia is a narrow country, structured around the Gambia River and surrounded by Senegal. In many inhabited areas, this geography makes it possible to extend the national grid rather than multiply standalone installations.

The government therefore presents grid connections as the most sustainable way to achieve universal access. This approach is set out in The Gambia’s National Energy Compact, adopted under the Mission 300 initiative, led in particular by the World Bank and the African Development Bank.

The document says that 73.7% of the population had access to electricity in 2024. It notes, however, that this figure did not yet include several projects completed or nearing completion at the end of 2025. The territorial gap remains significant: access exceeded 97% in Greater Banjul, but reached only about 45% of people in rural areas, according to data cited in the Compact.

Mini-grids and decentralised solar solutions have not been abandoned. They remain under consideration in locations where extending power lines would be too costly, technically difficult or incompatible with certain environmental constraints. But for now, they are not at the heart of national policy.

241 communities targeted in two inland regions

The contracts signed on 28 September 2026 cover 148 communities in the Central River region and 93 in Upper River. The work will be funded entirely from the national budget, a choice that sets this programme apart from several recent projects backed by external partners.

The project involves about 377 kilometres of medium-voltage lines, 248 kilometres of low-voltage networks and the installation of 219 distribution transformers. This equipment is intended to carry electricity to villages and then distribute it to households, public services and local businesses.

In Central River, Alpha TND will carry out the lot valued at about $8.8 million. It includes 223 kilometres of medium-voltage lines, 165 kilometres of low-voltage networks and 140 transformers.

In Upper River, Power Factor Limited will deliver a second lot worth about $5.35 million. The project includes 154 kilometres of medium-voltage lines, 83 kilometres of low-voltage networks and 79 transformers for the 93 communities concerned.

The announced contract period is 18 months. The authorities nevertheless want to speed up implementation to bring The Gambia closer to its goal of universal access before the global 2030 deadline.

Rural catch-up goes beyond simply connecting homes

For the people concerned, a power line means more than a household connection. It can extend shop opening hours, help preserve agricultural produce and improve the operation of schools and health facilities.

Small businesses also stand to benefit. In the Central River and Upper River regions, access to a more stable power supply could support grain processing, water pumping, refrigeration, welding and digital services. However, a physical connection does not automatically guarantee reliable service. The quality of distribution, the cost per kilowatt-hour and households’ ability to pay remain decisive.

National utility NAWEC, which is responsible for water and electricity, will therefore need to support the grid expansion with regular maintenance and better planning. The authorities have also asked companies to meet technical standards and recruit young people in the beneficiary regions.

This requirement addresses a common difficulty with major infrastructure projects: communities receive infrastructure, but few lasting jobs and little local capacity to maintain it. The programme’s success will therefore depend as much on maintaining the equipment as on building the lines.

Increase generation and reduce reliance on thermal power

Extending the grid addresses only part of the problem. The Gambia must also have enough generation to supply new users. The electricity system remains exposed to the costs of thermal power and regional imports.

The National Energy Compact sets a target to increase renewables’ share of the generation mix. It is expected to reach 30% in 2030, up from 13% in 2024, according to the document. The strategy includes developing solar power, strengthening transmission capacity and mobilising more private investment.

The Gambia already relies on its integration into the West African power system. Regional interconnections can enable electricity imports when domestic generation is insufficient, while also helping to reduce costs by providing access to more competitive sources of power across ECOWAS, the Economic Community of West African States.

This regional dependence also creates an additional obligation: to modernise the national grid to limit losses, stabilise voltage and accommodate variable solar generation. Without these investments, new connections could deliver formal access but an intermittent service.

A trend seen across West Africa

The Gambian programme forms part of a regional trend. In February 2026, the authorities announced the electrification of 719 communities through several projects. The government is now aiming for universal access by the end of 2026, while acknowledging that part of the population still lacks service.

The World Bank also approved $52.6 million in funding in May 2025 to strengthen transport and energy infrastructure in The Gambia, including connections for 80 rural communities. These projects show that the country is now combining the national budget, concessional financing and regional partnerships.

The next test will be twofold. It will be necessary to verify that the 241 communities are connected on schedule, then assess service continuity once the lines are energised. For people in the Gambian interior, universal access will not be measured by the arrival of electricity poles. It will be judged by the light available each evening, the functioning of public services and the ability to run a business without relying on a generator.

Automatic translation. Original French version